|
MULTIPURPOSE DOCK ON THE DELAWARE RIVER
PORT OF WILMINGTON, DELAWARE
------------------------------------------------------------------------------------------------------
Duffield Associates, Inc. was initially retained by the Diamond
State Port Corporation to complete a feasibility study for its first
new dock and berth on the Delaware River. The study involved: bathymetric
surveys; subsurface exploration, including land and water-based
borings and soil/environmental sampling to address both geotechnical
and environmental issues; location and configuration of the proposed
berth, including performing sediment transport analyses to determine
initial and maintenance dredging requirements; evaluation of dredging
material disposal options/sites; preliminary design of site roadways,
access causeways, and dock structure; identification of submerged
cultural resources and other environmental permitting issues, including
wetland area identification and mitigation; regulatory agency liaison;
and preparation of a preliminary construction cost estimate.
In conjunction with another engineering firm, a final design was
developed to include an 875-foot long pile-supported dock. The location
and orientation/configuration of the berth were developed to eliminate
initial and long-term maintenance dredging which would have taxed
the already capacity-challenged Wilmington Harbor.
Design services provided by Duffield Associates included technical
design of pile foundations to support the berth and trestle, which
traversed a Corps of Engineers containment dike, a 10 ft soil surcharge
to pre-consolidate a 17 acre paved parking lot over a former dredge
disposal area, analysis and design for relocation of several earthen
containment dikes over soft recently placed dredged materials and
pavement design over the unconsolidated dredged materials, existing
dikes and fast lands. Duffield Associates was subsequently retained
for construction review of Access Road and berth construction. Services
included: review of the test pile program (including review of splice
welds, axial load, and pile dynamic testing); production piles including
splice welds; bitumastic coating for production piles; earthwork;
and concrete activities.
Since completion of the initial construction in 2002, Duffield
Associates has been retained by the DSPC and DSPC's engineers and
contractors to provide additional design and construction review
services related to the 17-acre paved parking lot and a new mooring
dolphin located downstream of the berth. Duffield Associates' services
included:
- Design and construction review of a "wearing surface"
for the 17-acre lot to allow for the storage of bulk materials;
- Performance of a "desktop" geotechnical evaluation
for the new mooring dolphin utilizing water-based borings previously
performed by Duffield Associates;
- Assisting Diamond State Port Corporation's structural engineer
with the development of technical specifications for the pile
supported mooring dolphin and access catwalk; and
- Developing driving criteria and reviewing construction of the
piling (which included pile dynamic testing) for the mooring dolphin
and catwalk; as well as reviewing reinforcing steel and concrete
placement for the mooring dolphin.
|